Drawdown Dredging UPDATES

July 2026 

Draw-Down Dredging to Start Fall 2027 

The Waterford Waterway Management District (WWMD) voted to push a potential start date for the draw-down dredging project to Fall 2027.

On June 26, the Wisconsin Department of Natural Resources (DNR) approved the WWMD for a three-year drawdown order. This is a significant milestone in the effort to improve the waterway and marks the first time the WWMD received approval by the DNR to address the sediment buildup across the waterway. This is not the only permit/order needed to start the project. The drawdown order and dredging are permitted separately. The WWMD needed to secure the drawdown order prior to applying for a dredging permit. The current plan is to draw down the river by five feet each fall over three consecutive years. Year one allows the project management team to evaluate how the river system draws down and to assess how to best remove dredged material. During this time riparian owners could complete shoreline improvements and personal dredging projects (appropriate DNR permits still apply). In years, two and three exposed sediments would be mechanically removed using excavators and bulldozers.

After negations with the DNR, a start date of September 15 of each year was agreed upon. At a drawdown rate of 4 inches per 24 hours, it will take 15 days to achieve a drawdown of 5 feet. The drawdown process would be completed by October 1 of each year with no additional drawdown activities permittable after October 7th. The water level will retain the 5-foot draw-down until the spring thaw (see draw-down dredging summary below for more details).

The draw-down dredging project has several milestones to reach before the project gets the final go-ahead of the DNR. The WWMD is in the process of completing the dredging permit application. Additionally, the DNR is requiring the WWMD to apply for an Incidental Take Permit which will allow us to proceed with the draw down even if it might unintentionally "harm" or "harass", a protected species, provided the impacts are minimized and mitigated. This permit process is expected to take 4-6 months.

With additional permits needed and an earlier start date to draw down than WWMD was hoping for, the board made the unanimous decision to push the project’s start date back to Fall 2027. This allows for an additional 12-14 months to communicate with key stakeholders and pursue additional grants to help offset costs of the project. In June the Racine County Board awarded the WWMD $750,000 from Monsanto settlement funds. This initial seed money is a significant contribution to the project, but the board will seek additional state and federal funding as the total cost for this project is more than the settlement funds awarded. Conversations with elected officials have been ongoing and with approval from the DNR our project has developed significant momentum at the county and state levels.

The WWMD recognizes the significant impact this project will have on riparian owners, community members, visitors, and valued businesses. The WWMD acknowledges there will be many questions and challenges ahead and would like to share our plan for communication between now and the Fall of 2027, and until the project’s completion.

The WWMD is working with Baxter and Woodman, our project management team, to develop a Riparian Owner Resource Guide to address the following: 
- Project outline, dates, details and impacts o What riparian owners can do during draw-down 
- Links to guidance from DNR regarding the process for necessary permits and process for application for shoreline improvements and personal dredging
- What to do with dredged material o Resources to remove piers, docks and watercraft 
- Environmental impact and what to do if you see something during the project o FAQs and more
- WWMD Website will host project information, resource guide and contact information, as well as links to information about necessary permits/processes, and research.
- WWMD will present an update to the project at the 2026 WWMD Annual Meeting
- Riparian owner and community engagement events will be held to inform the public about the project
- WWMD will continue to communicate on key milestones as they are reached

WATERFORD WATERWAY 3 CONSECUTIVE YEAR DRAW DOWN – SUMMARY

Year 1 (Sept. 15, 2027 – Ice out Spring 2028)
- Draw-down river level by 5ft
- Allows for assessment and evaluation of the draw-down
- Contractors can inspect the site and evaluate for bidding purposes
- Riparian owners can perform shoreline, dock, and pier repairs and improvements
- If riparian owners have previously applied for and been awarded permits for individual dredging and shoreline improvements, these projects can be performed during draw-down

Year 2 (Sept. 15, 2028 – Ice Out Spring 2029)
- Draw-down river level by 5ft (or recommended level based on year 1 assessment)
- Main navigational lanes and channels are dredged using mechanical means
- Riparian owners can perform shoreline, dock, pier, repairs and improvements
- If riparian owners have previously applied for and been awarded permits for individual dredging and shoreline improvements, these projects can be performed during draw-down if owners have worked in collaboration with the WWMD dredging contractor to avoid any interruptions or interference with the main dredging project.
- Pre and post draw down assessments

Year 3 (Sept. 15, 2029 – Ice Out Spring 2030)
- Draw-down river level by 5ft (or recommended level based on year 2 assessment)
- Remaining main navigational lanes and channels are dredged using mechanical means
- Riparian owners can perform shoreline, dock, pier, repairs and improvements
- If riparian owners have previously applied for and been awarded permits for individual dredging and shoreline improvements, these projects can be performed during draw-down if owners have worked in collaboration with the WWMD dredging contractor to avoid any interruptions or interference with the main dredging project.
- Pre and post draw down assessments

Latest Information

May 13, 2026

The WWMD commissioners held a stakeholder workshop with the project leads for the draw down dredging. The purpose of this meeting was to discuss communications strategies moving forward with the working assumption that we get DNR approval. 

This meeting discussed a Riparian Resource Guide, communications strategies and the hosting of information on our website. The commission also discussed future work and needs of the district as the project moves forward. 

The WWMD is aware that communication to internal and external stakeholders will be critical moving forward. As of this meeting the board and project team were waiting for the necessary approvals from the Wisconsin DNR. 

April 13, 2026

Vote by riparian community passes to modify annual budget for the purposes outlined in our dredging project request. The WWMD will now move forward with soil sampling and approvals from the DNR. At the same time the WWMD and our engineers will be working to develop an updated timeline for riparian owners. 

The vote suggested strong support for a draw down dredging approach. Many riparian comments were heard and noted to be addressed by the WWMD and Engineers at future riparian owner workshops. The WWMD thanks the community for coming out and sharing their thoughts, concerns, and suggestions as this process moves forward. 

February 2026


The WWMD has taken the first step on January 15th towards permitting a major draw-down dredging project that would potentially start in 2027. The WWMD has partnered with Baxter & Woodman to serve as the project managers and coordinators for a draw-down dredge approach. Baxter & Woodman have extensive experience working with draw-down dredging projects across the state and region. They bring the experience and necessary expertise necessary to assist the WWMD in attaining our dredging goals.

We will do an initial draw down in October of 2026 that will allow our engineers to test the sediment, monitor the river’s path and let our owners clean up their shorelines.   In early spring the river and lake will be returned to the ordinary high-water mark, and typical lake and river recreation will return.

In winter of 2027, the major project will remove a minimum of 189,000 cubic yards of sediment from our waterway, after the river level has been reduced by 5 feet. Heavy machinery will be brought in to bulldoze and excavate the muck, restoring depths to the original hard bottom. It may take two seasons to remove the total desired amount of muck, but it will be worth it.

Please note that this is only an initial step - we are working toward a final plan

Once this plan is finalized we will be able to provide more information and address questions posed by the riparian community. The WWMD will only post updates on our official communication channels which include: WWMD website, Facebook posts/events/live updates, and official email listserv.

If you have questions please direct those to info@waterfordwwmd.com.

  

Ecosystem Restoration Dredging Project Over the Years

Summer 2025

The WWMD is finally at a point where we have some current pricing and real options to potentially move forward in 2026 with an Ecosystem Restoration project. If you recall, in 2022 a dredging plan was presented and ultimately voted down by the board. The second phase of that project was contingent upon a property that was being sold would eventually become available for use as a disposal site for over 50,000 cubic yards of sediment. That property is now available and in play for use as a disposal site.  Through research, referrals, and good fortune, we now have three options for restoring our waterway: -

1. Traditional hydraulic dredging, which involves pumping a sediment/water mix to a containment site, much like the Brown’s Lake Project, could result in 189,000 cubic yards of sediment being removed from our waterway at a price we should be able to accept.

2. Drawdown dredging, which involves drawing down the river prior to October 15th, would allow us to remove even more sediment, and history tells us that this could cost us 50% - 60% less than hydraulic dredging. Our engineers have prepared a proposal to get us there and a plan to start in 2026. 

3. Last, we have a new technology that is still being proven and tested in Wisconsin that has a tremendous upside and would not require us to utilize disposal sites, thousands of dump trucks, thousands of gallons of diesel consumption, dredging pipe or dredging personnel. The technology provides oxygen throughout the water column through nanobubbles and promotes consumption of the muck, as well as binding the phosphorus in our water and muck to an inert state, where it does not promote growth of undesirable weeds, reduces algae blooms, and improves water clarity. A pilot test study in central Wisconsin showed reduction of twelve inches of muck in seventy-five days in a 2 acre marina, and water went from less than six inches of visibility to twelve feet.

The WWMD received a proposal in late August 2025 for hydraulic dredging. The proposal is thorough, prepared by individuals with unparalleled knowledge of our waterway, and an eagerness to perform the work. Since our original bids in 2022 of $6,100,000 and $7,000,000, interest from dredging contractors has been hard to find, and the only realistic pricing we received was over $10,000,000. This unsolicited bid we recently received would achieve the 2022 goals and remove over 25% more sediment than that plan, at a price similar to the 2022 prices. This project involves thirty-five foot wide navigation lanes up to five feet deep in areas outside of the main river channel.

We approached one of our engineers, Geosyntech, in late June about leading us from concept to completion on a drawdown dredging project. This would involve lowering the water level using the Waterford dam to drop the water level five feet from the ordinary high water mark, likely in mid-October (latest possible date dictated by WI DNR). Once the exposed river/lakebed has frozen solid enough, contracted local grading companies would excavate the somewhat dried, frozen muck and haul it to nearby disposal sites. Likely in late February the dam would be adjusted to its typical position and water level would be restored to the level we are used to. Geosyntec has prepared a comprehensive plan and proposal with a project time frame spanning from 2026 to 2027.

The least developed plan is a nanobubbles project, which would involve investing in Molaear nanobubbles generators, strategically located throughout the waterway. Some of these devices require atypical electric power that is not normally found in residential neighborhoods. Others require powering from riparian homes. The equipment is quiet and minimally invasive from a visual perspective, and does not hinder navigation. The work that these machines do is not limited to a narrow navigation channel, only the distance in which they can pump out the bubbles. A similar project, still currently being implemented in central Wisconsin, came at a price of $8,000,000, and is being heavily watched and reviewed by the DNR. No negative side effects have been recorded as a result of their usage. There are over 600 installations of these systems worldwide. This option provides the entire waterway with clearer, cleaner water, potential to remove sediment naturally, reduce algae blooms, and reduce invasive aquatic plants.

September 24, 2019 – The DNR mandated a 2-year pilot study to include proof of concept to dredge and dewater 7,000 cubic yards removed from conservancy bay in year 1, with land spreading in year 2. This is basically a science project to see if we can do it. Information collected during this pilot study would determine the feasibility of the process and if successful, form the basis for engineering, plans, permits, bidding, and funding needed for the removal and disposal of the remaining material. Bidding for the pilot project was done in September. The one bid we received was for $1,999,750. Project management, contingencies and overhead push the budget to $2,325,000. The committee is not recommending proceeding with this proposal. Because this portion of the project did not go as expected, the pilot project will not happen as mandated by the DNR. Our efforts will shift from the anticipated contract negotiations to streamlining the project to eliminate unnecessary expenses and bring it back at a reasonable cost. The DNR will have to come up with a simpler, cheaper way to do the pilot (science) project to determine the feasibility of land spreading.

DNR Small Scale Dredging Permit

Updated May 26, 2019 – There is a small scale dredging general permit available from the DNR for riparian land owners for the navigational dredging of man-made impoundments (GP20), that was issued on September 27, 2018. It allows for the removal of up to 50 cubic yards of material per year from a waterway for the purposes of navigation. There are specific eligibility standards as well as a self-certification that an applicant is required to complete as part of the process which addresses the type of material being dredged.